Sprinkler System Project Plan
Weekend of Nov-9
- Cut grass and trim
- Pick up old sprinklers
- Get permit info
- Make modular connectors (bought them instead)
Week of Nov-13
- Get pressure issue resolved
- Get plans redrawn if necessary
Weekend of Nov-16
- Buy all hardware (7 man hours)
- Place flags for heads (1 man hour)
- Lay out pipe paths (6 man hours)
- Build kits (5 man hours)
Weekend of Nov-23
- Dig manifold pits (2 man hours)
- Trench (16 man hours)
- Prepare trenches for pipe (12 man hours)
Mon Nov-25
- Lay electric conduit in trenches (and insert wire)
Tues Nov-26
- Lay control wire conduit in trenches (and insert wire)
- Attach to main water line
Wed Nov-27
- Install manifolds
- Route wire from garage wall entry to master controls through 0.5" PVC pipe
- Connect wire to manifold controls
- Put together pipe in trenches
Thurs Nov-30
- Put together pipe in trenches
Friday Nov-31
- Put together pipe in trenches
Saturday Dec-1
- Put together pipe in trenches
Sunday Dec-2
Weekend of Dec-8
- Install heads
- Connect weatherproof outlets to breaker box (only if not wet)
Week of Dec-9
- Fill in remaining dirt in trenches (with dad)
- Install rain switch
- Adjust heads
- Clean up
|